About Us
Enertechnos is a pioneering clean-tech company dedicated to ‘delivering decarbonisation’.
Who we are
Enertechnos was founded with one vision in mind: to provide a solution to deliver decarbonisation. Soon enough, it became clear that whenever the question involves ‘decarbonisation’, the answer always involves ‘electricity’.




What we do
We invented and patented a concept called ‘Capacitive Transfer System’ (CTS), which reduces power delivery and, more importantly, can deliver more power through the same mass of conductor or operate at high frequencies than conventional legacy cables.


Who we are
Enertechnos was founded with one vision in mind: to provide a solution to deliver decarbonisation. Soon enough, it became clear that whenever the question involves ‘decarbonisation’, the answer always involves ‘electricity’.


What we do
We invented and patented a concept called ‘Capacitive Transfer System’ (CTS), which reduces power delivery and, more importantly, can deliver more power through the same mass of conductor or operate at high frequencies than conventional legacy cables.
CTS cables we have developed can be easily manufactured in existing factories on standard cable-making machinery.
While developing the CTS concept, a large part of the engineering effort in recent years has been to adapt CTS to multiple applications while designing cables that can be made in any existing cable factories. Enertechnos’ strategy is not to be a manufacturer but instead to license its technology to cable and hardware manufacturers around the world.
Market Opportunity
In 2020 the market globally for cable and wire was circa $90 billion and projected overall grid investments to transition to net zero by 2050 is around $14 trillion where 48% of that value is sustainment capital in replacing assets at end of life, 38% is for grid reinforcement and 21% is for new connections. At the same time we have to provide EV charging infrastructure to convert billions of existing fossil fuel driven vehicles to electric, decarbonise aviation with several thousands of airports and even legacy fossil fuel producers.
Market Opportunity
In 2020 the market globally for cable and wire was circa $90 billion and projected overall grid investments to transition to net zero by 2050 is around $14 trillion where 48% of that value is sustainment capital in replacing assets at end of life, 38% is for grid reinforcement and 21% is for new connections. At the same time we have to provide EV charging infrastructure to convert billions of existing fossil fuel driven vehicles to electric, decarbonise aviation with several thousands of airports and even legacy fossil fuel producers.
Progress to Date
Enertechnos has used equity to fund R&D since its start in 2014, successfully attaining the following milestones:
Commenced research based on wound capacitor, tested at Electrical research Association (ERA)
Manufacturing feasibility report commissioned from The Welding Institute (TWI)
Built own cable-making machinery and then the first CTS cable – flat (‘planar’) geometry
Highly successful testing programme proved concept was valid as linear cable
Designed round (annular’) version of CTS, commissioned from specialist cable company
Tested 1km long annular cable under National Physical Laboratory supervision
Designed first enamelled CTS cable
Commissioned enamelled cable from specialist cable company
Devised high-frequency testing rig to emulate length
Established Advisory Board of industry experts
Commenced work with leading UK distribution network operator
Continued testing of enamelled cable at high frequency
Moved into new Kingston premises
New patents submitted
Innovate UK project awarded and started, with Brunel University and TWI (The Welding Institute) as partners
Design of cable (two versions)
Ordered commercially-built ‘layered’ cable – 1km from major Portuguese manufacturer
Started work on joints with Lovink, Netherlands
Established Sheffield laboratory to test cable under Brunel University supervision
Ordered ‘enamelled’ cable from major Italian manufacturer
Concluded Sheffield tests with both layered and enamelled cable versions
Completed Innovate UK programme with award for ‘Best Environmental’ project
Joined Ofgem Environment Working Group
Commenced BEIS-funded Energy Entrepreneurs Fund, Round 7 (EEF7) programme with two phases:
- Phase 1: material testing at very high voltage
- Phase 2: use of CTS in wireless car charging applications
Built high-voltage test lab (up to 70kV) in Kingston
Continued EEF7 programme
Drafted design guidelines for CTS installations in grid networks
Designed cable protection system
Designed a CTS grid modelling methodology using DigSilent software package
Completed EEF7 project
Finalised joint design for underground cable with working prototypes
Launch of new business direction in electric vehicle (EV) charging
Launch of new business direction in aviation
Announced awinner of NZTC Open Innovation Programme and received funding
Want to get in touch?
We’re proud to be at the forefront of the clean tech industry and always looking for opportunities for our technology to be used across countries and industries.
Feel free to get in touch by clicking the link below.
Want to get in touch?
We’re proud to be at the forefront of the clean tech industry and always looking for opportunities for our technology to be used across countries and industries.
Feel free to get in touch by clicking the link below.